Steps of Framework for Climate Change Adaptation in HawaiiHow implementing/Plan to implementTimeline$$ funding and other CommentsPartnersStatus as of: 8/12/11

.

ABuild Climate Change Adaptation TeamORMP Policy Group, de factoongoing, unless determine other pathCZM federal (NOAA) funding

.

BDevelop and adopt a long-term visionDevelop Vision, Preferred Future, and Statewide Climate Change Policy at workshop on Aug 22-23, 2011 with ORMP partnersworkshop 8/22-23/11; submit draft leg to Gov office by 9/30/11CZM federal (NOAA) funding & USACE Silver Jackets fundingCZM, OP, ORMP, NOAA, USACE, LG office, other stakeholdersvision flushed out at 8/22-23/11 workshop with ORMP partners & other stakeholders

.

CIdentify Planning Areas and Opportunities Relevant to CCTBD, possible to work through ORMP working group - also, piece included in USACE PAS scope of workAug-Oct 2011ORMP, NOAA, USACEdraft in Framework; needs to be flushed out

.

DScope Climate Change Impacts to Major SectorsUH Sea Grant implementing with NOAA funding; Hawaii impacts report to stem from Pacific impacts report; outreach effort to coincide with release of document;
expected completion of HI report: Jan-Feb 2012; public outreach effort in Spring 2012$ UH SG funding
$ HTA funding
potential CZM federal (NOAA) funding
UHSG, ICAP, HTA, CZM/OP, Leg, countiesin progress

.

Employ impacts document to facilitate process with ORMP partners and focus groups to develop a compelling case for climate change adaptation and building political willASAP;
if get funding from NOAA, 7/1/12 -5/31/13
written into CZM's proposal for NOAA $309 Project of Special Merit (PSM) - $200K for 18 mo.CZM, OP, ORMP, NOAA, Legsmall group working on it w/o funds

.

E-FConduct Vulnerability and Risk Assessments for each SectorOMPO conducting vul. assessment for critical transportation assets on O'ahu;
expected completion Sept. 2011$ US FHWA grantOMPO, US FHWAin process

.

1 symposium to conduct risk and vul. assessments for CCH; proposing on sectors with less technical needs/data (possibly economic development)10/1/11 - 9/30/12$ NOAA CRest grant to UH ($300K for 2 years- $146,537 for yr. 1)ICAP, CZM/OP, NOAA PSC, ORMPgrant received; in progress

.

1 symposium to conduct risk and vul. assessments for another county; proposing on sectors with less technical needs/data (e.g., agriculture on Kauai or BI)10/1/12 - 9/30/13$ NOAA CRest grant to UH ($300K for 2 years: $153,463 for yr. 2)ICAP, CZM/OP, NOAA PSC, ORMPin progress

.

risk and vulnerability assessments for sectors w/ more technical data and needs and related to water resources - Phased approach by county. Phase 1 = CCH.8/22-11 - 8/21/12$USACE PAS funding ($200,00 for 1 year, Phase 1)USACE, CZM/OP, ICAP, ORMP, BOW, CWRM, CCH DPPCost Share Agreeement w/ scope of work being routed for signatures

.

Depending on status of above projects (and others), fill gaps in risk and vulnerability assessements; compile relevant documents for a draft State Adaptation Plan7/1/12 - 12/31/13$ NOAA 309 Project of Special Merit (PSM) - $200K for 18 mo.NOAA, ORMP, UHSG, UH SOESTProposal submitted to NOAA OCRM 9/8/11

.

Next Steps

.

GPrioritze Areas for Adaptation PlanningDepending on status of above projects (and others), may commence implementation of this step with NOAA 309 PSM $see D11see E11F11Proposal submitted to NOAA OCRM 9/8/11

.

HSet Preparedness Goals

.

IDevelop, Select, and Prioritze Preparedness Actions

.

JImplement Preparedness Plan

.

KMonitor Progress and Update Plan as Appropriate

.

.

.